The design life expectancy of a crane refers to the total number of working cycles that the crane can complete from the beginning of use to the final scrapping. Cycle refers to a complete process from lifting an item to the time when the next item can start to be lifted, including crane operation and normal rest in energy.

Ⅰ、The use level of the crane as follow:

Use level

Service life cycle

Description

U0

L≦16 thousand

Rarely used

U1

16 thousand< L ≦ 32 thousand

U2

32 thousand< L ≦ 63 thousand

U3

63 thousand< L ≦ 125 thousand

U4

125 thousand< L ≦ 250 thousand

Infrequent use

U5

250 thousand< L ≦ 500 thousand

Moderate use

U6

500 thousand< L ≦ 1 million

More frequent use

U7

1 million< L ≦ 2 million

Use frequently

U8

2 million< L ≦ 4 million

Extremely frequent use

U9

4 million≦ L

Ⅱ、Load state class as follow:

The ratio of the typical lifting capacity and the number of lifting times to the rated lifting capacity and the total number of lifting times within the design life expectancy.

Load level

Kp

Description

Q1

Kp ≦ 0.125

Rarely lift the rated load, and often lift the lighter load

Q2

0.125< Kp ≦ 0.25

Rarely lift rated load, often lift medium load

Q3

0.25< Kp ≦ 0.5

Sometimes the rated load is lifted, and the heavier load is lifted more often

Q4

0.5< Kp ≦ 1

Lift the rated load frequently

Ⅲ、Chinese standard crane working class

Load level

Kp

Use level (GB/T3811-2008)

U0

U1

U2

U3

U4

U5

U6

U7

U8

U9

Q1

Kp ≦ 0.125

A1

A1

A1

A2

A3

A4

A5

A6

A7

A8

Q2

0.125< Kp ≦ 0.25

A1

A1

A2

A3

A4

A5

A6

A7

A8

A8

Q3

0.25< Kp ≦ 0.5

A1

A2

A3

A4

A5

A6

A7

A8

A8

A8

Q4

0.5< Kp ≦ 1

A2

A3

A4

A5

A6

A7

A8

A8

A8

A8

Ⅳ、Crane working levels under different standards as follow:

Crane Working Class  &  Service Life

Standard

ISO/BS/DIN

M3

M4

M5

M6

M7

M8

GB/EN

A3

A4

A5

A6

A7

A8

FEM

1Bm

1Am

2m

3m

4m

5m

CMAA

B

C

D

E

F

-

HMI/ASME

H2

H3

H4

H5

H5

H6

Safe working Period SWP(h)

400

800

1,600

3,200

6,300

12,500

Lifting Motor Duty %ED

25

30

40

50

60

60

Starts (s/h)

150

180

240

300

360

360

Running Time(h)

3,200

6,300

12,500

25,000

50,000

100,000

Starts

480,000

1,134,000

3,000,000

7,500,000

18,000,000

42,000,000

Overloads

1,000

1,000

1,000

1,000

1,000

1,000